High Street Disruption from 28th Sept for 12 weeks

Transport for Buckinghamshire will be commencing maintenance works in the High Street to correct loose and uneven paving that can cause trip hazards.

The works are due to commence w/c Monday 28 September 2020 and will last for approximately 12 weeks. Site working hours will be from 08:00 to 17:00 Monday to Friday with perhaps some weekend and night working on areas that cannot be worked on during normal hours.

Some of the repair works required will affect the running lane of the carriageway, and will necessitate reducing High Street access between Corporation Street and Market Square, to enable areas of the stone paving to be re-laid/repaired more efficiently. See the map in the shop for details.